Landed cost
Landed cost for supplier quotes: the formula buyers actually need
Unit price is what the supplier charges per piece. Landed cost is what the piece costs after freight, duty, one-time charges, payment terms, and risk. The difference is often 10–30%.
The formula
Landed total = product subtotal + one-time charges + freight + duty + packaging + financing cost
Landed unit cost = landed total ÷ total quantity
Landed unit cost = landed total ÷ total quantity
A more conservative version adds a risk allowance:
Risk-adjusted total = landed total × (1 + risk score × risk premium)
For example, a 20% risk premium at a risk score of 50 means landed total × 1.10.
Worked example
| Line | Supplier A (FOB) | Supplier B (DDP) |
|---|---|---|
| Product subtotal | $21,000 | $23,500 |
| Printing + finish | $2,400 | $2,000 |
| Tooling | $850 | Included |
| Freight | Not quoted | $1,800 |
| Duty / clearance | Not included | Included (DDP) |
| Financing cost (30% deposit) | $70 | $77 (Net 30) |
| Landed total | $24,320 + freight + duty | $27,377 |
| Risk adjustment | +18% | 0% |
| Risk-adjusted | ~$28,700 | $27,377 |
Supplier A looks $3,000 cheaper on the headline. Once you add the missing freight, duty, and risk, Supplier B is the safer award.
What belongs in landed cost
- Product: material, printing, lamination, assembly, testing, certification.
- One-time: tooling, molds, plates, setup, sampling, proofing.
- Logistics: freight, insurance, packaging, pallets, crates, last-mile delivery.
- Import: duty, tariff, customs clearance, brokerage, import tax.
- Financing: deposit, prepayment, and payment-term cost.
- Risk: missing scope, short warranty, long lead time, quote expiry, unclear terms.
Common mistakes
- Comparing FOB to DDP without adding freight and duty to the FOB quote.
- Comparing unit price at different quantities or MOQs.
- Ignoring one-time tooling because it is not in the per-unit price.
- Treating a 50% deposit as free; it ties up cash for months.
- Assuming a missing line item means “included” rather than “unknown.”